Starter Relay [Skyactiv G 2.0]
GeneralRefrigerant Pressure Sensor Inspection [Manual Air Conditioner]
1. Install the manifold gauge.
2. Verify the high-pressure side reading of the manifold gauge.
3. Measure the terminal voltage at PCM terminals 2BB, 2AX and 2AJ
4. Using the graph below, measure and verify the terminal voltage at 2AX.
5. Follow the PCM inspection when measuring the other ter ...
Rear Window Defroster/Outer Mirror Heater
Outline
Fogging is cleared from the rear window and outer mirror glass by heating
of the filament.
Structural view
System wiring diagram
Vehicles with full-auto air conditioner system
Vehicles with manual air conditioner system
Construction
Rear window defroster
...
Liftgate Opener System
Outline
A liftgate opener system has been adopted in which the liftgate can be opened
just by pressing the liftgate opener switch.
The rear body control module (RBCM) performs liftgate opener system fail-safe..
Function
When the liftgate opener switch is pressed, the l ...