Purpose, Function
The starter relay supplies power to the starter by receiving the signal from the PCM.
Construction
The starter relay is installed to the relay and fuse block.
Operation
The contact point is on when the voltage is supplied to the coil based on the signal from the start stop unit, and the battery voltage is supplied to the starter.

Fail-safe
Function not equipped.
Starting System [Skyactiv G 2.0]
EngineClutch Pedal Position (CPP) Switch Inspection [Skyactiv G 2.0]
Continuity Inspection
1. Verify that the CPP switch is installed properly..
2. Disconnect the negative battery cable..
3. Disconnect the CPP switch connector.
4. Verify that the continuity between CPP switch terminals A and B when the clutch
pedal is depressed and when it is released is acc ...
Rear Body Control Module (Rbcm) Inspection
1. Disconnect the negative battery cable..
2. Remove the following parts:
a. Trunk board.
b. Trunk end trim.
c. Rear scuff plate (LH).
d. Trunk side trim (LH).
3. Remove the rear body control module (RBCM) from the body with the connector
connected..
4. Connect the negative battery c ...
Check Fuel Cap Warning Light
Purpose/Function
The check fuel cap warning light is built into the instrument cluster.
If the PCM detects that the fuel cap is open, the light illuminates to warn
the driver that the fuel cap is open.
Construction
Built into the instrument cluster.(See INSTRUMENT CLUS ...