1. Remove the pressure control valve assembly..
CAUTION:
Do not apply a pressure 36 kPa {0.37 kgf/cm2, 5.2 psi} or more. Doing so will damage the pressure control valve and evaporative hose.
2. Apply a pressure of 36 kPa {0.37 kgf/cm2, 5.2 psi} to port A.

3. Verify that there is airflow from port B.
If there is no airflow, replace the pressure control valve assembly..
Power Steering Malfunction Indicator Light
Pressure Control Valve [Skyactiv G 2.0]Check Valve
Except U.S.A. And CANADA
Purpose, function
The check valve maintain the pressure in the fuel tank at constant pressure.
Construction
The check valve is installed to the side of the charcoal canister.
Mainly consists of valve, umbrella, and spring.
O ...
Driveline/Axle SST
Front and Rear Axle
49 T028 3A0
Ball joint puller set
49 T028 301
Dust boot installer
49 U034 204
Dust boot installer
49 W032 310
Support block
—
— ...
On Board Diagnostic System Simulation Inspection [Fw6 A EL, Fw6 Ax EL]
1. Connect the M-MDS to the DLC-2.
2. After the vehicle is identified, select the following items from the initialization
screen of the M-MDS.
a. Select “DataLogger”.
b. Select “Modules”.
c. Select “TCM”.
3. Select the simulation items from the PID table.
4. Perform the act ...