Purpose
The system piping connects each related part of the refrigerant system.
Construction
Block-type piping has been adopted to the pipe connection, improving the efficiency of piping related servicing.
The pipes in the piping system consist of the following parts.
Cooler hose (HI)
Cooler hose (LO)
Cooler pipe
The pipes in the piping system are made of aluminum alloy and the hoses are made of rubber (flexible hose).
A high-pressure charging valve is located on the cooler pipe (HI) and a low-pressure charging valve is located on the cooler pipe (LO).

Fail-safe
Function not equipped.
Refrigerant Charging
Refrigerant Line Removal/InstallationGenerator Control [Skyactiv G 2.0]
Outline
Idling stability has been improved by optimum control of generator voltage
according to engine operation and electrical load conditions.
The PCM determines the engine operation and electrical load conditions based
on the input signals from each control part and controls ...
Starter [Skyactiv G 2.0]
Purpose, Function
The starter rotates the crankshaft via the ring gear and it serves as a trigger
to start the engine.
Construction
The starter is installed to the rear part of the engine on the left side.
The starter is a coaxial reduction type which can obt ...
A Pillar Trim Removal/Installation
1. Partially peel back the seaming welt.
2. Take the shaded area shown in the figure, and pull the A-pillar trim in the
direction of the arrow (1) while detaching clip A, clips B.
3. Cut the lead wire connecting clips B and grommet using a nipper.
4. Pull the A-pillar trim in the dir ...