1. Remove the push button start..
2. Verify that the continuity between the push button start terminals is as indicated in the table.


If the continuity can be verified as indicated in the table, go to the next step.
If not as indicated in the table, replace the push button start..
3. Apply battery positive voltage and connect the ground to the push button start terminals and verify that the LED illuminates as indicated in the table.


If the LED does not illuminate as indicated in the table, replace the push button start..
Pre Delivery Inspection
Push Button Start Removal/InstallationCanister Vent (Cv) Solenoid Valve
U.S.A. And CANADA
Purpose, function
Seals the atmosphere side of the charcoal canister during EVAP leak check
monitoring.
Construction
Included in the charcoal canister.
The CV solenoid valve is consists of O-rings.
Operation
According to the ...
Upper Cowl Side Reinforcement Removal [Panel Replacement]
Symbol Mark
Removal Procedure
1. Drill the 13 locations indicated by (A) shown in the figure.
2. Drill the 8 locations indicated by (B) shown in the figure.
NOTE:
When a drill the 8 locations indicated by (B) shown in the figure, the through
hole is not made in consideration of ...
Steering Shaft Inspection
1. Inspect the steering column for excessive play and damage.
2. Verify that the clearance between the projection on the steering column shown
in the figure and the bracket is less than 2.0 mm {0.079 in}.
If the clearance between the projection and bracket is 2.0 mm {0.079 in}
or ...