Chevrolet Spark manuals

Mazda CX-5 Service & Repair Manual: Quarter Window Glass Installation

Mazda CX-5 Service & Repair Manual / Body / Glass & Windows / Quarter Window Glass Installation

WARNING:

CAUTION:

1. Remove sealant along the perimeter of the glass using a razor or scraper. (when reusing the glass)

2. Clean and degrease the ceramic part along the perimeter of the glass.

3. Inspect the glass for cracks. If it is cracked, chamfer it using sandpaper.

4. If the glass is reused, attach pins and fastener to the glass as shown in the figure.


NOTE:

5. Apply glass primer along the hollowed marks in the ceramic coating on the new glass, along the sealant tracks on the reused glass, then allow it to dry for approx. 30 min.

CAUTION:

NOTE:


6. Cut away the old sealant using a razor or scraper so that 1—2 mm {0.04—0.07 in}

thickness of sealant remains along the perimeter of the frame.

7. If the sealant has come off completely in any one place, apply some primer after degreasing, and allow it approx. 30 min

to dry. Then apply 2 mm {0.07 in}

thickness of new sealant.

8. Clean and degrease the bonding surface along the perimeter of the body.

9. Apply body primer on the body as shown in the figure, then allow it to dry for approx. 30 min.

CAUTION:


10. After the primer has dried, apply 11 mm {0.43 in}

in thickness, 5 mm {0.20 in}

in width of sealant using a sealant gun. Where it is not applied properly, correctly apply it using a spatula.


11. Insert the positioning pins to the body and install the quarter window glass.

12. Verify that the gap at the upper and side parts of the glass is within the specification shown in the figure, then press along the perimeter of the glass.


13. Install the following parts:

a. C-pillar trim.

b. D-pillar trim.

c. Trunk side trim.

d. Rear scuff plate.

e. Trunk end trim.

f. Trunk board.

14. Connect the negative battery cable..

15. Allow the sealant to harden completely. Sealant hardening time: 24 h

Power Window System Preliminary Inspection [Power Window System]
Manual Open/Close Function Inspection STEP INSPECTION ACTION 1 Switch the ignition ON (engine off or on). ...

Quarter Window Glass Removal
1. Disconnect the negative battery cable.. 2. Remove the following parts: a. Trunk board. b. Trunk end trim. c. Rear scuff plate. d. Trunk side trim. e. D-pillar trim. f. C-pillar trim. ...

Other materials:

Front Bumper Removal/Installation
CAUTION: Affix the protective tape to the position (vehicle body side) shown in the figure to prevent scratches and damage. 1. Disconnect the negative battery cable.. 2. Remove fasteners A. 3. Pull the front over fender in the direction of the arrow shown in the figure ...

Generator Control [Skyactiv G 2.0]
Outline Idling stability has been improved by optimum control of generator voltage according to engine operation and electrical load conditions. The PCM determines the engine operation and electrical load conditions based on the input signals from each control part and controls ...

General Procedures (Front And Rear Axles)
Wheel and Tire Installation 1. When installing the wheels and tires, tighten the wheel nuts in a criss-cross pattern to the following tightening torque. Tightening torque 108—147 N·m {12—14 kgf·m, 80—108 ft·lbf} Suspension Links Removal/Installation 1. For the joint ...