Symbol Mark

Removal Procedure
1. Drill the 27 locations shown in the figure.

2. Remove the corner junction.
Corner Junction Installation [Panel Replacement]
Electric Variable Valve Timing Relay [Skyactiv G 2.0]Blind Spot Monitoring (Bsm) Off Switch
Purpose
The blind spot monitoring (BSM) system can be turned on or off optionally
by the driver.
Function
The switch operation signal is sent to the instrument cluster.
Construction
The BSM OFF switch is built into the cluster switch.
The resistance is bui ...
Hazard Warning Switch Inspection
1. Disconnect the negative battery cable..
2. Remove the decoration panel..
3. Verify that the continuity between the hazard warning switch terminals is
as indicated in the table.
If the continuity is as indicated in the table, go to the next step.
If not as indicated i ...
PID/Data Monitor Inspection [Instrument Cluster]
1. Connect the M-MDS to the DLC-2.
2. After the vehicle is identified, select the following items from the initialization
screen of the M-MDS.
a. Select “DataLogger”.
b. Select “Modules”.
c. Select “IC”.
3. Select the applicable PID from the PID table.
4. Verify the PID dat ...